Shop drawing review checklist for hotel furniture and joinery from Turkey

On each furniture shop drawing, check the sizes against the site and the design drawings, the sections and joints, the material and finish codes, the hardware, the wall fixings, the electrical cut-outs, the tolerances and the revision clouds. Return each sheet with a status code: A approved, B approved with comments, C revise and resubmit, D rejected. A review takes days per package, and every resubmission restarts the clock, so a clean first pass saves weeks.

Sheet GD-21Reviewed Rovers Contract

A shop drawing is the factory’s drawing of what it will build: each piece, its joints and its finishes. Until it is approved, a change costs a pen stroke; after approval, the factory cuts. Turkish partner factories issue shop drawings for each item on a hotel order. Rovers checks them against the BOQ and the design drawings before they reach the designer, and the designer’s review then decides what gets made.

The checklist per sheet

Check What to look for
Title block Item code matches the FF&E schedule; drawing number; revision letter; date; scale
Overall sizes W × D × H against the design drawing and against site sizes from the survey
Site fit Wall-to-wall runs, ceiling heights, door swings, skirting, columns and risers
Plans, elevations, sections A section through every joint that matters: carcass, top, plinth, drawer, headboard to wall
Material and core Board type and thickness (for example 18 mm MDF), solid timber species, moisture-resistant board near water
Finish codes Every face carries a finish code that matches an approved sample: veneer, lacquer sheen, laminate, metal
Edges Edge type and thickness per edge (solid lipping, ABS, veneer), and which edges are exposed
Hardware Brand and model of runners, hinges, locks, handles, with finish; load ratings where shown
Fixings How each piece fixes to the wall or floor, what the wall is, anti-tip fixing on tall units
Electrical cut-outs Sockets, USB, switches, reading lights, cable routes and grommets: position from the finished floor and wall
Appliances Minibar, safe, TV bracket: model, cut-out size and ventilation gap
Upholstery Frame, foam grade and density, fabric code, fire standard for the market
Tolerances Stated tolerance on overall size and on the gap to walls; scribe allowance on fitted joinery
Quantities Count per room type matches the schedule
Revision clouds Every change since the last issue is clouded and listed in the revision table

Read the sections first. Most site problems trace back to a joint nobody drew: a headboard that hides a socket, a desk top that meets a wall that isn’t straight, a wardrobe that can’t pass the door.

Status codes

Return each sheet with one status. Many consultants use the four letters below. The contract may use its own set: the US Army Corps of Engineers, for example, runs codes from A to G, where C is “approved, resubmission required” and E is “disapproved”.

Code Meaning Can the factory start?
A Approved, no comments Yes
B Approved with comments Yes, with the comments built in; corrected sheets are resubmitted for record
C Revise and resubmit No. The sheet comes back revised and is reviewed again
D Rejected (or for information only, where so marked) No. A new submission is needed

Write comments on the sheet, next to the detail they refer to, in a colour that copies well. A comment that says “check” without saying what is right sends the sheet round again.

How long reviews take

There is no single standard. The contract sets the review period. As a reference point, the US federal guide specification for submittals (UFGS 01 33 00, August 2026) sets 30 calendar days for review, and says each resubmittal gets the same period as the first.

On a hotel order, the review period is set per package in the programme. Two things keep it short:

  1. Package by family. Send all casegoods for one room type together, then upholstery, then joinery, so the reviewer sees related pieces side by side.
  2. One round of comments. A sheet that goes A or B on the first pass goes into production. Each C adds a full review period to that item’s lead time.

Production dates are counted from approved drawings and approved samples, not from the order date. A late approval moves the delivery date by the same amount.

What Rovers checks before you see a sheet

Every sheet is checked against the BOQ line, the design drawing and the site survey, and every finish code against the sample register. Questions the factory can’t answer from the drawings are sent as a short list with the submission, so they are answered once.

What to send us

Send the design drawings, the FF&E schedule, the finish schedule, any site survey and the review period your contract sets. Shop drawings come back per package, with a sheet register and a status column ready for your codes.

Sources
  1. Construct & Commission: Status A, B, C and D, what they mean (J. Curtis, updated 23 Feb 2026) · accessed 2026-10-04
  2. US Army Corps of Engineers RMS/QCS: what the submittal codes mean (A approved as submitted, B approved except as noted, C approved resubmission required, E disapproved) · accessed 2026-10-04
  3. WBDG: UFGS 01 33 00 Submittal Procedures (August 2026), review within 30 calendar days; resubmittal review period same as initial · accessed 2026-10-04
Sheet 09Start an orderRev COpenReply within one business day

Send the project the way you already work.

Email the files, message us on WhatsApp, or use the short form. A named engineer replies within one business day, with the questions we need answered before pricing.

  1. You send drawings or BOQ, or just the room count.
  2. An engineer reads it and asks what's missing.
  3. You get one quote, every line priced, the factory chosen per item.
  4. Samples and shop drawings, then production.

Your reference W-···· · quote it in any message

Email · recommended for filesEmail the drawings or BOQprojects@roverscontract.com · any size, any format, copy your team inOpen email →
Or the short form
Add drawings or BOQ (optional)PDF, DWG, XLSX, images · up to 50 MB each