How an order runs, from your drawings to handover

You send drawings or a BOQ. We read every line, price it with the Turkish factory that fits each item, and run it through shop drawings, samples, production, inspection and shipping. One team answers for it until handover.

Sheet HW-01Rovers Contract

Lead times start when you approve the shop drawings, not when you place the order: the factory can only start cutting once drawings are approved.

The steps

StepWhat happensWhat you receive
OP-00
You send the project
Drawings, a BOQ or FF&E schedule, renders, or just the room count and the opening date.A reference number and a reply the same business day.
OP-05
We read every line
Our engineer reads the drawings and the BOQ, lists what is missing, and writes down the assumptions that change the price.One short list of questions, with assumptions stated.
OP-08
We choose the factory per item
Each item goes to the partner factory that fits it on style, price, capacity and lead time. Casegoods, upholstery and metal can go to different lanes.An itemised quote in USD: every line priced, Incoterm and lead time stated.
OP-10
Shop drawings
Every coded item is drawn with its elevation, section and build-up, hardware and fixings.A drawing set to mark up and approve. Nothing is cut before you sign.
OP-20
Samples and finishes
Veneers, lacquers, fabrics and hardware come to you as physical samples, each with a code that stays on the drawings and the BOQ.Samples and an approval record.
OP-25
Mock-up room (if you want one)
For larger hotels, one finished room is built on the factory floor before the batch.A visit or a live video walk-through, then your approval.
OP-30…70
Production
The factories make the items. Our engineer follows each lane on the floor.A weekly report with progress by item and photos by operation.
OP-80
Inspection before packing
Each batch is measured against the approved drawing: dimensions, finish against the sample, hardware, stability.An inspection report with the numbers. You can add a third-party inspector.
OP-90
Packing by room
Items are packed and labelled by floor and room, piece n of m, with a crate list.A packing list that matches your room schedule.
OP-100
Shipping and documents
By road or sea, on the Incoterm you chose. Export documents and the certificate of origin prepared.One set of shipping documents for the order.
OP-110
Delivery and installation
Delivered to site by floor. Outside the United States, installation can be part of the package; in the US we manufacture and deliver.Delivery notes, then a snag list.
OP-120
Handover
Snags closed, spare stock handed over, care notes for each material.A handover certificate and the warranty terms.

Who does what

WorkRoversPartner factory
Reading drawings and BOQYesSees the stripped pack it is asked to price
Choosing the factoryYes, per item—
Shop drawingsPrepared and checked before they reach youProduction details
ProductionFollowed on the floorYes
Inspection before packingYes, against the approved drawingIts own checks as well
Packing, documents, shippingCoordinated as one orderPacks to our standard
Your single point of contactYes—

The documents you receive

Every order runs on the same paperwork. These are samples from one illustrative order, so you can see the format before you send anything. The sample documents page has a sample quotation as a PDF.

SAMPLE ORDER RC-0142 · SAMPLE 180-key hotel · Riyadh · illustrative data

Programme

W1W3W5W7W9W11W13W15W17W19W21EngineeringShop drawings SD-*Rev C approvedSamplesMAT-* samplesMock-up roomCasegoodsHB, NS, WD, DKUpholsteryHeadboard panels, chairsQCBatch inspectionsLogisticsPack · ship · deliverDrawings approvedMock-up signedFinal inspectionOn siteTODAY · W14

Document register

CodeDocumentRevDateStatus
SD-HB-01Shop drawing · headboard wall panelCWk 5Approved
SD-WD-02Shop drawing · wardrobe + minibar unitCWk 5Approved
MAT-OAK-01Sample approval · oak veneer, PU 30 GUBWk 6Approved
MAT-FAB-03Sample approval · quilted panel fabricBWk 6Approved
MU-0142Mock-up room reportAWk 7Approved
PR-0142-W14Weekly production report—Wk 14Issued
QC-WD-02-014Inspection report · WD-02 batch 1AWk 14Passed
QC-HB-01-015Inspection report · HB-01 batch 2AWk 15Waiting
PL-0142-01Packing list · floor 4—Wk 17Pending

Inspection report · QC-WD-02-014

WD-02 · wardrobe + minibar unit · Batch 1 · 60 pcs · sampled 8 pcs (AQL 2.5, level II) · dimensions in mm

CheckNominalToleranceMeasuredResult
Overall height2 400±1.02 400.4Pass
Overall width1 600±1.01 599.6Pass
Overall depth618±0.5618.2Pass
Door gap3.0±0.53.3Pass
Door flush (face to face)0.0≤0.40.2Pass
Finish gloss (60°)30 GU±528 GUPass
Colour vs MAT-OAK-01matchvisual, D65matchPass
Hinge soft-close110°functionokPass

Load plan and packing label

40' HC · 12 032 × 2 352 mm internal · loaded by floor and roomCRATE 412-ACRATE 412-BCRATE 412-CCRATE 413-ACRATE 413-BCRATE 413-CCRATE 414-ACRATE 414-BDOORS
RC-0142CRATE 412-A
Room412
Floor4
ItemWD-02
Piece1 of 2
RC0142·412A·WD02·01

What to send us

Whatever you have. A BOQ or FF&E schedule is ideal. Drawings and renders without a list are fine: we take the quantities off the drawings and the finishes off the renders, and tell you what we assumed. If you only have a room count and an opening date, start there.

Sheet 09Start an orderRev COpenReply within one business day

Send the project the way you already work.

Email the files, message us on WhatsApp, or use the short form. A named engineer replies within one business day, with the questions we need answered before pricing.

  1. You send drawings or BOQ, or just the room count.
  2. An engineer reads it and asks what's missing.
  3. You get one quote, every line priced, the factory chosen per item.
  4. Samples and shop drawings, then production.

Your reference W-···· · quote it in any message

Email · recommended for filesEmail the drawings or BOQprojects@roverscontract.com · any size, any format, copy your team inOpen email →
Or the short form
Add drawings or BOQ (optional)PDF, DWG, XLSX, images · up to 50 MB each